Montwood Drive Construction Update: November 21, 2014

PAVING ACTIVITIES

On Montwood:

The contractor is demolishing the pavement and preparing the subgrade for future paving activities North of the Montwood and Wedgewood intersection.

Workers are paving the outer and inner lane, as well as the driveways on Montwood, from Linum to the gas station (Valero).

UTILITY AND SIDEWALK WORK

On Montwood Drive:

Contractor is installing landscaping and a decorative rock wall on Montwood between Honolulu and Camwood.

Contractor is also pouring the concrete for the walls and tops of the box culverts at the intersection of Montwood and Wedgewood.

Wedgewood is presently closed immediately north of Montwood. Posted detours remain in place along Montwood Drive between McRae and Yarbrough. Eastbound and westbound traffic will continue traveling in the lanes south of the median.  

*Information provided by City of El Paso Engineering and Construction Management Department