PAVING ACTIVITIES

On Montwood:

The contractor has started to prepare the area on Montwood between Fir and Camwood for future paving activities.

UTILITY AND SIDEWALK WORK

On Montwood Drive:

The contractor has just recently finished pouring concrete for the walls, tops and floors for the box culverts on Montwood between Linum and Wedgewood.

Workers finished pouring the concrete for the sidewalks and driveways on Montwood between Honolulu and Monaco, and they also installed the curbson Montwood between Monaco and Camwood.

DETOURS

Posted detours remain in place along Montwood Drive between McRae and Yarbrough. Eastbound and westbound traffic will continue traveling in the lanes south of the median.  

-Information provided by City of El Paso, Engineering and Construction Management Department